Concrete

Cement, sand and metal for any slab, beam, column or footing

Element
Grade
Adjust assumptions
×
%
kg

Result

2.50 m³

88.29 ft³ of concrete

  • Cement 17 bags 16.63 bags incl. 5% wastage
  • Sand 0.41 cubes 1.16 m³
  • Metal / aggregate 0.82 cubes 2.31 m³
  • Steel (rough) 210 kg At 80 kg per m³ — engineer to confirm
  • Water 396 litres
How we calculated this
  1. Wet volume 5 × 4 × 0.125 × 1 = 2.50 m³
  2. Dry volume 2.50 m³ × 1.54 = 3.85 m³
  3. Cement 3.85 × 1/7 × 1440 kg/m³ ÷ 50 kg = 15.84 bags; +5% = 16.63 → 17 bags
  4. Sand 3.85 × 2/7 × (1 + 5%) ÷ 2.832 = 0.41 cubes
  5. Metal 3.85 × 4/7 × (1 + 5%) ÷ 2.832 = 0.82 cubes
  6. Water 792 kg cement × 0.5 = 396 litres
  7. Steel 2.50 m³ × 80 kg/m³ × (1 + 5%) = 210 kg

Estimates are for budgeting and checking quotes, not structural design. Have a qualified engineer confirm quantities and reinforcement before building.